A470 – Surfacing

The scheme was a 5.7km long single carriageway Trunk Road in Mid Wales.

Client: Welsh Government
Location: Builth
Date: 2009-2011
Value: £35m

 

An ECI contract requiring delivery of the scheme through publication of draft orders, public inquiry, publication of orders, and detailed design and construction.

A Public Inquiry (PI) was held in July 2009 over a four week period. No objections were maintained by any of the statutory bodies. This was achieved by closely working with the relevant bodies throughout the development of the scheme.

Following the successful PI, we were awarded the design and build contract and was completed ahead of time in December 2011.

 

Construction

  • 5.7km of single carriageway with 3.5m verges
  • Earthworks – 430,000m3
  • 3 major bridges across rail and river
  • Attenuation ponds – 7 no.